Commonwealth Avenue Bridge lane closures expected until December
Lanes close at either end of the bridge in both directions during set work hours until December.
The bridge works help finish Stage 1 of the Commonwealth Avenue Bridge renewal, with Stage 2 to follow. The National Capital Authority says lanes close at either end of the bridge, in both directions, during work hours.
Work hours are 9:30 am to 4 pm on weekdays, and 7 am to 5 pm on weekends. Evoenergy will also start essential work to relocate a high-voltage power supply for the project.
Motorists should expect temporary traffic changes on Commonwealth Avenue from now until December. The authority thanked people for their patience, and for travelling carefully or taking other routes.
- 9:30 am to 4 pm
- Weekday work hours
- 7 am to 5 pm
- Weekend work hours
- 31 October to 1 November
- Rail replacement buses
- Early 2027
- Main construction finish
Why it mattersKnowing the set work hours lets drivers plan routes and avoid the lane closures.
AustraliaAnyone driving on Commonwealth Avenue in Canberra should expect changes until December.